Development Phases — Overview
✓
Phase 1 — Industrial Design & Initiation
Completed · March 2026
02
Phase 2 — Structural DFM + PCBA Development
Active · ~40% complete · Est. Jun 2026
03
Phase 3 — Engineering Validation (EVT)
Pending · Q3 2026
04
Phase 4 — Pilot Production + Certification
Pending · Q3–Q4 2026
Recent Activity
Action RequiredApr 24, 2026
3rd structural CAD review (V3) completed. Three high-priority design changes required before 2nd prototype build: temple arm folding interference, sharp corner temporal pressure, insufficient nose bridge flex. All assigned to Zhang Qing.
ElectricalApr 17, 2026
Mainboard PCBA schematic review started. Dual MIPI SC233HGS array with FSYNC sync confirmed on SSC8826Q. Camera module PCBA prototyping scheduled — samples expected May 5, 2026.
MilestoneApr 7, 2026
Project management plan finalised. Nine-phase roadmap confirmed with full team assignments across structural, electrical, and production workstreams.
KickoffMar 20, 2026
Project kicked off. Mainboard definition, appearance brief, functional requirements, and BOM scope confirmed with MicroAGI. Factory NDA signed. Reference CWX-2026-0001 assigned.